(print version - 1 page PDF file)
1.0 Purpose
To present the procedure for the procurement of equipment from outside
vendors
2.0 Note
New Equipment > $1000 but <$5000
No RFQ is required on purchases less than $5000, but Purchasing requires a
copy of the vendor quote. In most cases, a sole RFQ may be sent to the vendor to
confirm the pricing, terms & conditions of the sale and delivery & install
information.
New Equipment > $5000 but < $100,000
A formal RFQ is required on all purchases over $5000 and the request must be
Posted on the Georgia Procurement Registry for a minimum of 15 working days or a
valid Sole Source form must be completed by the requestor and approved by
Purchasing resulting in a sole RFQ. A copy of the quote from the preferred
manufacturer is also required.
New Equipment > $100,000
The request must be forwarded to the Dept of Administrative Services in
Atlanta to be bid out and awarded, except highly technical equipment
New Equipment > $250,000
The request must be approved by the Board of Regents (BOR) and the Office of
Planning and Budget (OPB) in Atlanta prior to starting the RFQ processes.
Used Equipment
Usually Sole Sourced, but not always and a Used Equipment form must be
completed.
EXCEPTION
All Contract purchases are exempt from the RFQ process but still must be
approved by BOR and OPB if over $250,000.
3.0 Procedure: Equipment
Responsibility: Department
Responsibility: Special Approval Departments (ITD and/or Grants Office)
Responsibility: Purchasing