Renovation / Relocation Checklist

Purpose: To inform User Groups involved in a renovation and/or relocation of the steps required.  If you have questions regarding this checklist please contact Facilities planning at (706) 721- 2691.  

1. User Department

Responsibility: Consults with Facilities Planning for Renovation projects (Facilities Planning does not work within MCG Health Inc.) to determine appropriate action to be taken.

Procedure: User prepares one of the following: 1) Inter-Departmental Request (IDR) Form MC-492; 2) Physical Plant Form MC-527; 3) Renovation/Cost Estimate Request Form.

Request for Moving Services (rev.11/17/97)

Responsibility: In the case of relocations, fill out and submit the Web Form, "Relocation Notice"

This form should be submitted as soon as possible once a relocation is planned.

2. Facilities Planning

Responsibility: Prepares documents for all renovations, coordinates construction and maintains Facilities Inventory.

Procedure: User notifies Facilities Planning of all relocations so as to maintain current Facilities Inventory.

3. Physical Plant/Work Management Center

Responsibility: Coordinates and executes items not requiring a renovation (i.e., keys, locks, signage, maintenance, etc.)

Procedure: User prepares Physical Plant IDR Form MC-527 and submits IDR to Building Coordinator for processing.

NOTE: Submit IDR for locks a minimum of 16 weeks in advance, and for signage a minimum of 6 weeks in advance.

4. ITD/Telecommunications

Responsibility: Assists in planning and installing telephone and communication system(s).

Procedure: User determines its needs with the assistance of Telecommunications. Telecommunications prepares a written recommendation when needed. User prepares Telephone Work Order Request Form.

NOTE: Submit Telephone Work Order Request for small moves (1-7 lines with up to 8 telephones) a minimum of 2-4 weeks in advance, and larger moves a minimum of 4-6 weeks in advance.

5. ITD/Information Systems Processing

Responsibility: Coordinates all computer acquisitions and installation.

Procedure: User coordinates with Computer Services early in the planning process (at least 4 weeks notice) to assure proper coordination of existing and/or new computer equipment. User submits IDR Form MC-492 for installation of cabling and/or computers.

6. Supply Administration/Purchasing

Responsibility: Coordinates the acquisition of all new furniture and equipment.

Procedure: User submits a Departmental Request.

7. Supply Administration/Asset Management/Moving Services

Responsibility: Coordinates the relocation of all loose furniture and equipment.

Procedure: User submits a request for moving services to Asset Management to relocate furniture and equipment.

NOTE: All moves are taken on a first come first serve basis. Submit requests for small moves (1-3 offices) a minimum of 48 hours in advance, and larger moves a minimum of 7 days in advance. It is recommended, however, that requests be made a minimum of 2-3 weeks in advance. User submits a list of all items to be moved and a copy of their equipment inventory listing(s) showing the updated changes.

8. Supply Administration/Campus Mail Services

Responsibility: Coordinates all mail services.

Procedure: User notifies Mail Services of the relocation and the date it will take place. It is suggested that the user show change of address on all correspondence.

9. Public Safety

Responsibility: Provides for the safety of individuals and property at MCG. Coordinates the allocation of parking areas.

Procedure: User notifies Public Safety a minimum of 2-3 days in advance of the relocation and the date it will take place so they can patrol the old and new locations. User may also need to contact Public Safety regarding parking.

10. Human Resources

Responsibility: Coordinates processing of Personnel Action Requests (PAR) to update Personnel Catalogs and Personnel Payroll File Maintenance System.

Procedure: User submits a change PAR for each individual, complete PAR block 008 to identify new location and block 010 if office extension changes.

11. Copy Center

Responsibility: Coordinates the relocation of all photocopiers with appropriate vendor and Supply Administration.

Procedure: The User should contact the Copy Center 5 working days in advance to the relocation of the copier.

Proceed to Relocation Notice Form.

Prepared by Facilities Planning
Revised: October, 2000


Copyright 2003
Medical College of Georgia
All rights reserved.

Facilities Management  |  Medical College of Georgia
Please email comments, suggestions or questions to:
Jonathan Bangs, jbangs@mcg.edu.

September 22, 2003